Zoyo Hillside Plots

Construction updates

Every milestone at Zoyo Hillside Plots, newest first, with photographs from the site.

Updated 15 Sep 20262 updates

Back to the project

15 Sep 2026

Water and sewer lines in progress

Underground water and sewer lines are 60% complete across Phase 1.

15 May 2026

Boundary wall completed

The boundary wall and main gate structure are complete.